[ALERT] Major System Outages for University Energy Savings Project - Building Closure February 7-8-9

Physics facility information via facility_info facility_info at lists.osu.edu
Mon Jan 6 16:37:35 EST 2020


Tri-annual preventive maintenance and major system outages associated with the University Energy Savings Project will occur in the PRB on February 7-8-9.

These work packages are highly impactful to all building environmental systems.

Consequently, occupants should take care to consider the implications of this work to their research plans and to make suitable preparations.

A tip sheet is being prepared to more fully explain the work packages and will be shared at a later date.

In the meantime, this message serves to provide the below day-by-day summary and is considered to be notice 1 of 3 for this work.

Friday February 7th

- Normal tri-annual preventive maintenance originally scheduled for January 8th is shifted to this date

- Process Cooling Water System: controls conversion, system offline all day

- Heating Hot Water System: controls conversion, system offline all day

- Steam System: controls conversion, system offline all day

- Building Chilled Water System: controls conversion, system offline all day

- Air Handlers 1 thru 4 (all units): normal preventive maintenance, systems offline at various times all day

- Exhaust Fans 1 thru 6 (all units): normal preventive maintenance, systems offline at various times all day

- Building closure beginning at 7:00 pm (accommodation for special needs for entering building will be maintained as in past building closures)


Saturday February 8th

- Building closed all day (accommodation for special needs for entering building will be maintained as in past building closures)

- Air Handlers 1 thru 3: controls conversion, systems offline all day

- Exhaust Fans 1 thru 6 (all units): controls conversion, systems offline all day


Sunday February 9th

- Building closed all day (accommodation for special needs for entering building will be maintained as in past building closures)

- Air Handler 4, system offline all day

- Performance adjustments and commissioning of all systems modified during the work campaign


Monday February 10th

- Building re-opened

- Commissioning and adjustments of all modified systems (as needed)


Tuesday February 11th

- Commissioning and adjustments of all modified systems (as needed)
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.osu.edu/pipermail/physics-staff-df/attachments/20200106/8158929f/attachment.html>