[ALERT] Air Handler 2 - Lab Side - North End - Returned to 100%

Physics facility information facility_info at groups.asc.ohio-state.edu
Tue Feb 5 12:00:13 EST 2013


Work crews have completed two of the four louver installations in the area well.

AHU-2 is returned to 100% capacity and all six main exhaust fans are back on line.

A similar outage may be required in coming days to complete the remaining two louver installations.