[CRITICAL] Process Cooling Water at Elevated Temperatures and Air Handlers Offline
Physics facility information via facility_info
facility_info at lists.osu.edu
Sun Apr 14 13:52:41 EDT 2019
Root cause details are unclear, but the following critical environmental and process conditions are currently present in PRB and either began or were also present as early as yesterday morning.
1.) Air Handlers 1 and 2 serving lab side are offline.
2.) Air Handler 3 serving office side is offline.
3.) Process Cooling Water is flowing but at elevated temperature - currently above 95 deg F.
4.) Exhaust fans are offline.
5.) Labs and Computer Farm Rooms are at elevated temperatures.
FOD is onsite and working to resolve the conditions, but is struggling with weekend personnel limitations.
Additional updates will follow as more details are known.
In the meantime, labs with occupants present in the building should check process cooling water circuits and close valves and shut down equipment as necessary.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.osu.edu/pipermail/physics-staff-df/attachments/20190414/64d6eeb7/attachment.html>
-------------- next part --------------
_______________________________________________
facility_info mailing list
More information about the physics-staff-df
mailing list