[ALERT] January 9th Next Quarterly Maintenance Shutdown - Notice 2 of 3
Physics facility information
facility_info at groups.asc.ohio-state.edu
Wed Dec 26 09:14:19 EST 2012
Quarterly PM (planned maintenance) on the PRB's four air handler units and six connected exhaust fans will be conducted by FOD on Wednesday, January 9, 2013.
Maintenance is scheduled to start at 7:00 AM and is planned to be completed by no later than 3:00 PM.
Because the lab side air handlers and connected exhaust fans will be shut down, fume hood operations should be suspended for the full maintenance period.
Occupants are reminded that although the building will remain open and accessible, air flows and other air-related building processes will be impacted throughout the day as maintenance is done.
In addition to normal PM activities, the final piping connections will be made for the nitrogen gas feed line from the PRB liquid nitrogen storage dewar to the CBEC site.
Please take planned action to prepare for this event.
Key Summary Points
- Air handler / Exhaust Fan shut down Wednesday, January 9th.
- No building closure or evacuation
- Suspend fume hood operations
- Building air flow and air-related processes will be interrupted throughout the day
- Final piping connections for nitrogen gas to CBEC will be made
For long range planning purposes, the 2013 quarterly maintenance dates are planned as follows:
Q1-2013 = January 9th Wednesday - Announced
Q2-2013 = April 10th Wednesday - Planned
Q3-2013 = July 10th Wednesday - Planned
Q4-2013 = October 9th Wednesday - Planned
This message is Notice 2 of 3 of such alerts
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.osu.edu/pipermail/physics-staff-df/attachments/20121226/93d30f8e/attachment.html>
-------------- next part --------------
_______________________________________________
FACILITY_INFO mailing list
More information about the physics-staff-df
mailing list