Triannual planned maintenance on the PRB's lab-side and office-side air handler units and exhaust fans will be conducted by FOD on Wednesday, May 3rd, 2017
Occupants are reminded that air flows and other air-related building processes will be impacted throughout the day as maintenance is done.
In addition to work on the air handlers, the Domestic Cold Water service will be shut down for repairs.
Maintenance and/or repairs will also be done on several other building systems not listed that are considered non-impacting to occupants.
Maintenance is scheduled to start at 7:00 AM and is planned to be completed by no later than 3:00 PM.
Please take planned action to prepare for this event.
Key Summary Points:
-Air handler / Exhaust Fan shut down Wednesday, May 3rd.
-Building air flow and air-related processes will be interrupted throughout the day.
-Domestic Cold Water service interruption
For long range planning purposes, the dates for Triannual Preventive Maintenance Activities for the calendar year
2017 are as follows:
Outage 1 - 2017: January 4 - Wednesday - Done
Outage 2 - 2017: May 3 - Wednesday - Announced
Outage 3 - 2107: September 6 - Wednesday - Planned
This message is Notice 2 of 3 of such alerts
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.osu.edu/pipermail/physics-other/attachments/20170417/b512d13f/attachment.html>
-------------- next part --------------
_______________________________________________
facility_info mailing list
More information about the physics-other
mailing list