[Cbe-grads] Nitrogen outage In CBEC
McCoy, Anthony
mccoy.287 at osu.edu
Wed Oct 16 09:53:45 EDT 2024
Good morning!
Step 1 of the nitrogen outage is complete. Nitrogen to the building is back on.
Nitrogen in 071, 073, 075 and 081 is still off.
Anthony
From: McCoy, Anthony
Sent: Tuesday, October 15, 2024 2:35 PM
To: _ENG CBE Graduate Students <ENG-cbe-gradstudents at osu.edu>; _ENG CBE Staff <ENG-cbe-staff at osu.edu>; _ENG CBE Researchers <ENG-cbe-researchers at osu.edu>; Reategui, Eduardo <reategui.8 at osu.edu>; Sangoro, Joshua <sangoro.1 at osu.edu>; Liu, X. Margaret <liu.482 at osu.edu>; Chalmers, Jeffrey <chalmers.1 at osu.edu>; Yang, Shang-Tian <yang.15 at osu.edu>
Subject: RE: Nitrogen outage In CBEC
Good afternoon,
This is a reminder of the nitrogen outage scheduled for portions of CBEC tomorrow. Please see message below for details, and let me know if there are any questions!
We have been trying to track down a large nitrogen leak throughout CBEC. I wanted to make everyone aware of a nitrogen outage in CBEC on Wednesday October 16th. Please read carefully as there are 2 different steps to this outage. This outage will only affect the north side of the building. Please close all ports/ nitrogen feeds to equipment Tuesday night. I will send out an email when nitrogen is restored.
CBEC Nitrogen Outage
Wednesday October 16th
Step 1 North side of building shutdown
Impacts 071, 073, 075, 081, 090, 092, 170, 190, 270, 290, 370, 390 470, 490
Isolation valves will be installed in the basement on the north side.
8am-12pm(noon) 4-hour outage
Work will take place in the hallway of the basement
Once work is finished on step 1 Nitrogen will be turned back on to the building. Rooms 071, 073, 075, 081 will not be turned on at this time.
Step 2 Labs in Basement on the northwest side
Isolation valve will be installed inside 071, 073, 075, 081
Nitrogen in these rooms will be down from 8am till 330pm
Work will take place in the ceiling above the northern fume hood bench
Thank you!
Anthony
From: McCoy, Anthony <mccoy.287 at osu.edu<mailto:mccoy.287 at osu.edu>>
Sent: Thursday, October 10, 2024 10:47 AM
To: _ENG CBE Graduate Students <ENG-cbe-gradstudents at osu.edu<mailto:ENG-cbe-gradstudents at osu.edu>>; _ENG CBE Staff <ENG-cbe-staff at osu.edu<mailto:ENG-cbe-staff at osu.edu>>; _ENG CBE Researchers <ENG-cbe-researchers at osu.edu<mailto:ENG-cbe-researchers at osu.edu>>; Reategui, Eduardo <reategui.8 at osu.edu<mailto:reategui.8 at osu.edu>>; Sangoro, Joshua <sangoro.1 at osu.edu<mailto:sangoro.1 at osu.edu>>; Liu, X. Margaret <liu.482 at osu.edu<mailto:liu.482 at osu.edu>>; Chalmers, Jeffrey <chalmers.1 at osu.edu<mailto:chalmers.1 at osu.edu>>; Yang, Shang-Tian <yang.15 at osu.edu<mailto:yang.15 at osu.edu>>
Subject: FW: Nitrogen outage In CBEC
Good morning!
Please see message below about an upcoming nitrogen outage in CBEC. Let me know if you have any questions or issues with the schedule.
Thank you!
Anthony
From: Williams, Walter <williams.5141 at osu.edu<mailto:williams.5141 at osu.edu>>
Sent: Wednesday, October 9, 2024 2:48 PM
To: ASC cbc-facilities-management <cbc-facilities-management at osu.edu<mailto:cbc-facilities-management at osu.edu>>
Cc: McCoy, Anthony <mccoy.287 at osu.edu<mailto:mccoy.287 at osu.edu>>; Kearns, Lance <kearns.157 at osu.edu<mailto:kearns.157 at osu.edu>>
Subject: Nitrogen outage In CBEC
Hello,
We have been trying to track down a large nitrogen leak throughout CBEC. I wanted to make everyone aware of a nitrogen outage in CBEC on Wednesday October 16th. Please read carefully as there are 2 different steps to this outage. This outage will only affect the north side of the building. Please close all ports/ nitrogen feeds to equipment Tuesday night. I will send out an email when nitrogen is restored.
CBEC Nitrogen Outage
Wednesday October 16th
Step 1 North side of building shutdown
Impacts 071, 073, 075, 081, 090, 092, 170, 190, 270, 290, 370, 390 470, 490
Isolation valves will be installed in the basement on the north side.
8am-12pm(noon) 4-hour outage
Work will take place in the hallway of the basement
Once work is finished on step 1 Nitrogen will be turned back on to the building. Rooms 071, 073, 075, 081 will not be turned on at this time.
Step 2 Labs in Basement on the northwest side
Isolation valve will be installed inside 071, 073, 075, 081
Nitrogen in these rooms will be down from 8am till 330pm
Work will take place in the ceiling above the northern fume hood bench
Please plan accordingly
Thanks,
Walter Williams
College of Arts and Sciences Department of Chemistry and Biochemistry
Manager-Building Services
165 CBEC| 151 W. Woodruff Ave
Columbus, Ohio 43210
614-292-2669
Williams.5141 at osu.edu<mailto:Williams.5141 at osu.edu>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.osu.edu/pipermail/cbe-grads/attachments/20241016/4c902115/attachment.html>
More information about the Cbe-grads
mailing list